For a data centre, backup power is not simply another piece of site infrastructure. It is the final line of defence against service disruption when mains power is lost.

Generators may remain on standby for long periods, but when an outage occurs, they must start immediately and continue operating reliably. That makes the condition of the fuel storage and delivery system just as important as the generators themselves.

PETRO Industrial recently supported a large-scale data centre project in Darwin with a customised fuel storage solution designed around this exact requirement. The project included nine purpose-built generator skid tanks connected to a remote 68,000-litre bulk fuel storage tank.

However, supplying the tanks was only the beginning. PETRO is also supporting the ongoing condition of the stored fuel and associated infrastructure through scheduled fuel circulation and quality testing.

Nine purpose-built generator skid tanks

The project required nine low-profile diesel tanks, each designed to sit directly beneath an individual standby generator.

PETRO Industrial Data center bulk fuel supply tanks

Each tank was manufactured with:

  • 1,000-litre safe-fill capacity
  • Approximate dimensions of 3,450 × 1,450 × 313 mm
  • A low-profile design suitable for generator mounting
  • Connections configured for integration with the wider fuel system
  • Heavy-duty construction for critical infrastructure use

The dimensions and connection points needed to work with the generator configuration and the broader site design. Rather than adapting a standard tank to fit, PETRO manufactured the skid tanks specifically for the application.

The completed arrangement allows each generator to draw from its dedicated tank while the nine skid tanks are supplied by a larger bulk storage system located elsewhere on the site.

Illustrative purpose showing a power generator installed ontop of the data centre bulk fuel tanks

Centralised storage with fuel available at each generator

A 68,000-litre bulk diesel tank provides the site’s main reserve of generator fuel.

From this central storage point, diesel is distributed to the individual 1,000-litre skid tanks beneath the generators. This gives the facility substantial bulk storage capacity while maintaining fuel availability at each generator location.

For critical infrastructure, designing the system this way provides several practical advantages:

  • Fuel can be stored centrally and distributed where required.
  • Each generator has a dedicated local fuel supply.
  • The system can support multiple standby generators across the facility.
  • Fuel storage can be planned around the site layout and required operating capacity.
  • The bulk tank, transfer equipment, pipework and generator tanks operate as one coordinated system.

But storage capacity alone does not guarantee generator readiness.

Stored fuel still needs to be managed

Diesel held for standby power may spend far more time in storage than fuel used in vehicles or regularly operating equipment.

During extended storage, fuel can be affected by water, condensation, particulate contamination and microbial activity. These issues may contribute to blocked filters, restricted fuel flow, pump wear or unreliable generator performance if they are not identified and addressed.

In Darwin’s hot and humid conditions, having a proactive fuel maintenance program is especially valuable.

A tank may be full and a generator may pass a routine mechanical inspection, but that does not automatically confirm that the fuel feeding it remains suitable for reliable use.

For a data centre, discovering a fuel-related problem during a critical power failure is far too late.

Image shows the PETRO Fuel quality and transfer service capability

Fuel circulation and testing every six months

To help maintain the system’s readiness, the stored diesel is circulated every six months and tested to confirm its condition.

Regular circulation helps prevent fuel from remaining stagnant in isolated sections of the storage and distribution system. It also provides an opportunity to operate the transfer infrastructure and identify potential problems before emergency operation is required.

Fuel testing provides visibility into what is happening inside the system—not simply what can be seen from the outside of the tank.

Depending on the site requirements and test program, fuel condition assessments can help identify concerns such as:

  • Water contamination
  • Sediment and suspended particulate
  • Microbial contamination
  • Changes in the condition of stored diesel
  • Contamination that may affect filters, pumps, or generator fuel systems

The results allow maintenance decisions to be based on evidence. If the fuel remains in suitable condition, that can be documented. If deterioration or contamination is detected, corrective action can be planned before reliability is compromised.

Looking beyond the fuel itself

Fuel readiness also depends on the equipment responsible for moving it.

Pumps, filters, valves, hoses, pipework, and controls all contribute to the successful delivery of diesel from the bulk tank to the generator skid tanks. A weakness anywhere along that path can affect the performance of the complete backup power system.

PETRO Industrial tanks are built to the hightest standards going through rigorous testing

A preventative maintenance approach can include:

  • Inspecting pumping and transfer equipment
  • Checking filters and replacing them when required
  • Examining connections, valves and accessible pipework
  • Confirming fuel can circulate through the intended system
  • Inspecting for visible leaks, deterioration or damage
  • Reviewing fuel test results and recommending further action
  • Polishing or remediating fuel when its condition requires intervention

This changes fuel maintenance from a reactive task into a planned part of the site’s resilience strategy.

One partner for storage, transfer and fuel quality

PETRO Industrial’s involvement does not have to end when the tanks are delivered.

We can assist with the complete fuel lifecycle—from customised bulk and generator storage through to pumping systems, fuel transfer, ongoing testing, preventative maintenance and fuel remediation.

For data-centre operators, consultants and infrastructure contractors, this creates a more coordinated approach:

  1. Design the fuel storage solution around the generator and site requirements.
  2. Integrate the bulk tank, transfer equipment and generator skid tanks.
  3. Establish an appropriate inspection, circulation and fuel-testing schedule.
  4. Monitor fuel condition and equipment performance over time.
  5. Take corrective action before an issue threatens backup-power availability.

The objective is straightforward: when mains power fails, the site should not be left questioning whether its stored fuel and transfer infrastructure are ready.

Image of Custom Data centre tanks

Is your backup fuel genuinely ready?

A large volume of stored diesel may provide theoretical runtime, but genuine power resilience depends on whether that fuel can be delivered cleanly and reliably when required.

PETRO Industrial supports data centres and other critical facilities with customised fuel storage, pumping and transfer systems, fuel quality testing, fuel polishing and preventative maintenance services.

Because backup power should be ready before it is needed—not investigated after the lights go out.

Talk to PETRO Industrial about a customised critical-power fuel solution or book a Fuel Quality Assessment.